CP-7(6): Inability to Return to Primary Site

Control Family:

Contingency Planning

CSF v1.1 References:

Threats Addressed:

Baselines:

(Not part of any baseline)

Previous Version:

Control Statement

Plan and prepare for circumstances that preclude returning to the primary processing site.

Supplemental Guidance

There may be situations that preclude an organization from returning to the primary processing site such as if a natural disaster (e.g., flood or a hurricane) damaged or destroyed a facility and it was determined that rebuilding in the same location was not prudent.